Project Details
Comprehensive production restoration at Campo Urdaneta, starting from a base of 2,000 barrels of crude per day and reaching the 13,500 barrels per day target in less than a year.
Scope of Work
- 01
Surface equipment repair and replacement
- 02
Installation of electro-submersible and progressive cavity pump systems
- 03
Well rehabilitation and intervention services
- 04
Gas lift automation implementation
- 05
Diluent distribution network automation
- 06
Maintenance of production facilities, including the García Sweetening Plant
- 07
Platform and infrastructure repairs
Results
- Production increased by 675%, from 2,000 barrels per day to up to 13.5 MBD in less than a year
- Non-productive operational time reduced from 50 days to 7 days
- Approximately 220 local and international employees took part in the recovery