Temporary production facility services for the wells of Macolla 21 at the Petromonagas Operation Center (San Tomé District – Ayacucho Division), incorporating four wells into the production stream.
Scope of Work
- 01
Connections for the incorporation of four wells into the production stream
- 02
Installation of tanks and vacuum units for fluid transportation in the San Tomé District
- 03
Temporary cleaning lines that increased crude extraction volumes
- 04
Design of preliminary structures and installation of frac (fractionation) tanks for collection
- 05
Construction and repair of pipeline infrastructure to convey crude to the main trunk line